ADS-SHR-DOC-SPECTECH
  • UiTM/T2/PER/SHR/B/0625/0003
  • MEMBEKAL,MENGHANTAR,MEMASANG DAN MENGUJILARI UNINTERRUPTIBLE POWER SUPPLY DIMAKMAL PENGAJIAN KEJURUTERAAN MEKANIKAL CAWANGAN TERENGGANU KAMPUS BUKIT BESI,DUNGUN TERENGGANU
  • Uninterruptible Power Supply (UPS)
  • UNINTERRUPTIBLE POWER SUPPLY (UPS) 60kVA
  • 1 Unit

Maklumat Spesifikasi Teknikal

  
Keterangan Calit Tawaran/Catatan
1. EQUIPMENT SPECIFICATION -
I. Location : MAKMAL PEMESINAN TERMAJU
Ya

Tidak
II. Brand : Please Specify
Ya

Tidak
III. Model : PBRDG-T3-60KS
Ya

Tidak
IV. Total Capacity - 60kVA / 60kW
Ya

Tidak
V. Phase - 3-Phase In / 3-Phase Out
Ya

Tidak
VI. BATTERY TYPE
-
A ) VRLA (MB) Maintenance Free Battery – min 3min backup time based on 53% of UPS capacity.
(Battery Brand: Preferable Minutebank or equivalent and must submission of battery backup calculation table justification)
Ya

Tidak
VII. BATTERY SPECIFICATION
-
A ) Nominal Voltage: 12V
Ya

Tidak
B ) Internal Resistance (In full charge status): ≈11.6 m Ohm
Standard Terminals: T04
Ya

Tidak
C ) Designed floating charging service life: 8 years (25°C)
Ya

Tidak
D ) Certified as meeting the requirements of ISO 9001:2015,ISO 14001-2015, ISO 45001-2018, CE certificate (Please provide Certificate from Principal)
Ya

Tidak
VIII. INPUT
-
A ) Nominal voltage - 3 x 380/400/415VAC (3PH+N)
Ya

Tidak
B ) Voltage Range - -30% ~ +20%
Ya

Tidak
C ) Frequency Range - 46Hz ~ 64Hz
Ya

Tidak
D ) Input Power Factor - 0.99 @ 100% Load
Ya

Tidak
IX. OUTPUT
-
A ) Nominal voltage - 3 x 360/380/400/415VA (3Ph+N)
Ya

Tidak
B ) Output Power Factor - 1.0
Ya

Tidak
C ) AC Voltage Regulation - ±1% (Batt. Mode)
Ya

Tidak
D ) Nominal Frequency - 50Hz ±0.1Hz or 60Hz ±0.1Hz
Ya

Tidak
E ) Frequency Range (Synchronized) -46Hz ~ 54Hz or 56Hz ~ 64Hz
Ya

Tidak
F ) Transfer Time - AC mode to Batt. Mode @ Zero
Ya

Tidak
G ) Inverter to Bypass – Zero
Ya

Tidak
H ) Waveform - Pure Sinewave
Ya

Tidak
I ) Overload Capacity - 100 - 110% for 60min, 110-125% for 10min, >150% immediately
Ya

Tidak
J ) Harmonic Distortion - ≤1% THDv (Linear Load); ≤3% THDv (Non-Linear Load)
Ya

Tidak
K ) Efficiency - Up to 99% (ECO mode)
Ya

Tidak
X. BATTERY CHARGER
-
A ) Charging Current (Max) - 1.0A - 20.0A (Adjustable)
Ya

Tidak
B ) Charging Voltage - ± 13.65V x N (N= 16-20)
Ya

Tidak
C ) Battery Quantity - 32 – 40 pcs (Adjustable)
Ya

Tidak
XI. STATUS INDICATOR
-
A ) LCD Display - 4.3" LCD Touch Screen Colour
LCD Display Panel (UPS Status, Load Level,
Input/Output Voltage, Discharge Timer, UPS Fault)
Ya

Tidak
B ) Audible Alarm - Battery Mode, Low Battery, Overload, UPS Fault
Ya

Tidak
XII. COMMUNICATION
-
A ) Power Management Software - RP Smart Power Management Software: Supports Windows Family, Linux & MAC
Ya

Tidak
B ) Interface - RS 232 / USB Port
Ya

Tidak
C ) SNMP Module - RP DA806 version support for real time dynamic remote monitoring through network connection
Ya

Tidak
D ) EPO - Yes
Ya

Tidak
XIII. PHYSICAL
-
A ) Operation Environment - 0 - 40°C, <95% non-condensing
Ya

Tidak
B ) Noise Level - < 70dbB @ 1 meter
Ya

Tidak
C ) Dimension (DxWxH)mm - 815 x 300 x 1000mm
Ya

Tidak
D ) Weight - 74 Kgs
Ya

Tidak
XIV. INTERNATIONAL STANDARD REQUIREMENT
-
A ) Safety Requirements:IEC/EN62040-1
Ya

Tidak
B ) EMI:Conducted Emission: IEC/EN62040-2 (Category C3)
Radiated Emission: IEC/EN62040-2 (Category C3)
Ya

Tidak
C ) EMS:ESD: IEC/EN 61000-4-2 Level 4
RS: IEC/EN 61000-4-3 Level 4
EFT: IEC/EN 61000-4-4 Level 4
Surge: IEC/EN 61000-4-5 Level 4
CS: IEC/EN 61000-4-6 Level 3
Power Frequency Magnetic Field: IEC/CN 61000-4-8 Level 4
Low Frequency Signals: IEC/EN 61000-2-2
Ya

Tidak
XV. Cabinet – L1050*D450*H970 x 3tiers
Ya

Tidak
2. INSTALLATION, TESTING & COMMISSIONING -
I. The tenderer should be responsible for the installation, commissioning and test-run of the equipment to the satisfaction of UNIVERSITI TEKNOLOGI MARA before final acceptance.
Ya

Tidak
II. All other related materials, components and cabling (electrical wiring i.e. from distribution board to machine location, isolator etc) which are not specified but required to ensure full proper operation of the above equipment, must be supplied and all related costs must be borne by the tenderer/supplier.
Ya

Tidak
III. Commissioning report should be submitted upon successful completion of the work within two (2) weeks.
Ya

Tidak
3. TRAINING -
I. Basic training UiTM for at least eight (8) personnel. The training should be a minimum of four (4) working days.
Ya

Tidak
II. The period of training shall be extended until all personnel involved are confident and competent enough to do the running and operation of the equipment.
Ya

Tidak
III. Areas of training to be covered preferably are:
  1. Operation of the whole system.
  2. Maintenance and general care procedures.
  3. Course materials, syllabus contents and training schedule should be provided in details
Ya

Tidak
4. AFTER SALES SERVICE -
I. The tenderer shall have technical background and experience in supplying and servicing of the equipment.
Ya

Tidak
II. A letter of support from the equipment manufacturer to the supplier must be attached.
Ya

Tidak
III. The installer will be responsible for service/maintenance visits after 6 and 12 months from the date of commissioning
Ya

Tidak
5. WARRANTY PERIOD -
I. The tenderer must provide at least 1-years warranty for the hardware and 1 years for battery.
Ya

Tidak
II. 1-Years On-Site Site Warranty and Support inclusive of Battery, Parts & Labour (8x5, Next Business Day) (Important: Please provide supported letter from Principal)
Ya

Tidak
III. The warranty period must not be less than one (1) year from the date of the complete handling over. The tenderer shall also clearly state the terms of warranty covering the equipment.
Ya

Tidak
IV. All labour and parts needed during the warranty period shall be borne by the tenderer. Any exclusion shall be clearly specified by the tenderer.
Ya

Tidak
6. MAINTENANCE -
I. The tenderer is required to deliver and perform installation, design, consultation, provisioning, migration, integration and commissioning work on the proposed solution from the current infrastructure to the proposed solutions. (Important: Please provide drawing/SLD from Principal)
Ya

Tidak
II. Minimum of 2 times Preventive Maintenance within 1 year. (By certified UPS principal)
Ya

Tidak
III. Preventive maintenance must include generate UPS health log report and batteries health report and able to obtain the dynamic password by authorized certified engineer/principle.
Ya

Tidak
IV. Full maintenance support for all items of equipment/software must be available locally. The engineering support shall be provided by competent personnel. The tenderer will have to indicate how they intend to meet these requirements, including naming the facilities available and their location. The maintenance period must not be less than one (1) year from the date of the complete handling over.
Ya

Tidak