|
1. GENERAL REQUIREMENT
|
-
|
|
|
I. The proposed item must be new, not refurbished.
|
Ya Tidak
|
|
|
II. The tenderer must ensure the availability, operability, reliability and functionality of the supplied itemcomponents to function properly.
|
Ya Tidak
|
|
|
III. All other related material, components, cabling and accessories, which are required to ensure fulloperation and integration with new or existing equipment of the item, must be provided by the tenderer.
|
Ya Tidak
|
|
|
IV. The tenderer must make sure all works are done properly without any damage to the existinginfra/equipment. The tenderer shall be responsible for any damage that occurs.
|
Ya Tidak
|
|
|
V. The tenderer MUST supply an equivalent or better equipment model from the same product family.
|
Ya Tidak
|
|
|
VI. The tenderer should ensure all existing network equipment/component/cabling is functioning before and afterproject implementation. The tenderer shall be responsible for any damage that occurs.
|
Ya Tidak
|
|
|
2. TECHNICAL REQUIREMENT
|
-
|
|
|
I. Singlemode Mode Fiber 10Gbps type E. (22 units) - Single Mode Type E :
|
-
|
|
|
A ) Support IEEE 802.3ae
|
Ya Tidak
|
|
|
B ) SC/LC Type Connector.
|
Ya Tidak
|
|
|
C ) Wavelength support up to 1310nm
|
Ya Tidak
|
|
|
D ) Singlemode Mode Fiber type
|
Ya Tidak
|
|
|
E ) Support cabling distance maximum : 10km
|
Ya Tidak
|
|
|
F ) Support minimum -8.2dBm to -0.5dBm transmission sensitivity
|
Ya Tidak
|
|
|
G ) Support minimum -0dBm to -14.4dBm receiver sensitivity
|
Ya Tidak
|
|
|
H ) Protocol-independent
|
Ya Tidak
|
|
|
I ) Less than one-third the power and size of MSA optic
|
Ya Tidak
|
|
|
J ) Transceiver should be hot-swappable
|
Ya Tidak
|
|
|
K ) Support RoHS 5 or 6 compliant
|
Ya Tidak
|
|
|
L ) Comply to International Safety Standards : EN 60825-1
|
Ya Tidak
|
|
|
3. INSTALLATION, TESTING AND COMMISSIONING
|
-
|
|
|
I. All necessary adapters, cables, and other accessories required shall be provided.
|
Ya Tidak
|
|
|
II. The tenderer is required to perform the installation, testing, and commissioning on-site for the supplied item at the location specified by UiTM.
|
Ya Tidak
|
|
|
III. The tenderer shall prepare a complete and comprehensive commissioning report in a form of hardcopy and softcopy after delivery, installation, and testing to ensure the item and accompanying software or the whole package has adhered to the satisfaction of UNIVERSITI TEKNOLOGI MARA before the final acceptance.
|
Ya Tidak
|
|
|
IV. The comprehensive commissioning report must include the User Acceptance Test. The tenderer must also include other additional documents as proof if requested by UiTM.
|
Ya Tidak
|
|
|
V. To perform testing and commissioning after completion of installation SFP Transceiver.
|
Ya Tidak
|
|
|
VI. Tenderer must submit the SFP Transceiver testing report in hardcopy after testing.
|
Ya Tidak
|
|
|
VII. Any cost related to installation and configuration shall be borne by the tenderer.
|
Ya Tidak
|
|
|
4. WARRANTY AND TECHNICAL SUPPORT
|
-
|
|
|
I. One (1) year of maintenance support consists of equipment faulty replacement (Next Business Day) and software upgrade shall be provided.
|
Ya Tidak
|
|
|
II. Response time to attend to a problem call breakdown of equipment or component is MAXIMUM 4 hours. The support must be within 8 hours of working days.
|
Ya Tidak
|
|
|
III. The warranty period will begin after the installation and testing is complete.
|
Ya Tidak
|
|
|
5. SUPPORTING DOCUMENTS
|
-
|
|
|
I. TENDERER MUST PROVIDE THE FOLLOWING SUPPORTING DOCUMENTS AND MUST BE PRESENTED IN THIS DOKUMEN TEKNIKAL
** PLEASE DO NOT DISCLOSE COMPANY INFORMATION BY ERASING THE INFORMATION RELATED TO COMPANY (NAME, LOGO, REGISTRATION NUMBER, ETC) FOR ALL DOCUMENTS REQUIRED HERE.
|
-
|
|
|
II. CATALOGUES / BROCHURES:
|
-
|
|
|
A ) All related catalogues or brochures shall be provided by the tenderer in Dokumen Teknikal.
|
Ya Tidak
|
|
|
III. LETTER OF AUTHORIZATION
|
-
|
|
|
A ) The tenderer must ensure the transceiver supplied are genuine products from Principle. Please attach a Letter of Authorization (LOA) from the Principal/Distributors.
|
Ya Tidak
|
|
|
IV. LETTER OF WARRANTY
|
-
|
|
|
A ) All components shall have a period of at least 1 year (according to respective item). Extended Product and Application Warranty from the date of installation against defects in materials and/or workmanship. Please attach the Letter of Warranty (LOW) from the Principal/Distributor.
|
Ya Tidak
|
|